Recently, Shanxi Weihe Power Plant 2×300MW units FGD retrofit and super-cleaning emission project, Yuanda Engineering’s 1st WESP project outside CPI group, started formally. At the stage of basic design, Yuanda Engineering organized site survey and repeated argumentations on project overall layout and design proposal. The finalized technical proposal is to reinforce original absorber and add a de-duster at the top of absorber. This proposal has following merits: less land occupancy, no separate waste water collection system and less flue gas system resistance. Unit 3 is planned to be completed on 30th, June and Unit 4 on 30th, October. Before start-up, Yuanda Engineering organized safety training and test for construction personnel and made safety technical disclosure. Designers jointly checked construction proposals such as construction drawings, de-duster installation and absorber reinforcing, etc. All preparations lay a solid foundation for subsequent project installation and construction.
|